Front Of The Home
Wide angle of the front of the home that we completed this project in.
Back of The Home
Wide angle of the rear of the home that we completed this project in.
Front Wall of The Basement Before
Here we can see how the front wall of the basement looked before we stated our demolition to install our patented systems.
Left Side of The Basement Before
Here we can see how the left side of the basement looked before we stated our demolition to install our patented systems.
Back Wall of The Basement
Here we can see how the back wall of the basement by the oil tank and boiler looked before we stated our demolition to install our patented systems.
Right Side of The Basement
Here we can see how the right side of the basement looked before we stated our demolition to install our patented systems.
CarbonArmor
In order to give regitity to this basement that was having bowing issues with its wall we strategically place CarbonArmor along the right side of the basement.
Starting Point
Our starting point for removing material from their concrete slab in order to install our waterproofing system.
Left Side Jackhammering
We jackhammered on the left side of their basement in order to create a trench to install our waterproofing system.
Sump Pit
Before installing our TripleSafe sump pump system during the jackhammering process we carved out our proper size pit for our basin.
Jackhammering Around Their Boiler & Oil Tank
We jackhammered around their boiler and oil tank in order to create a trench to install our waterproofing system.
Right Side Jackhammering
We jackhammered on the right side of their basement in order to create a trench to install our waterproofing system.
Jackhammering For Days
Because of the size of this basement our Installation Specialists felt as though they were jackhammering forever.
Left Side of The Basement
After digging our trench we started the process to install our FlowGuard waterproofing system. This process starts by us installing perforated pipe around the perimeter of the basement.
Back Wall By The Boiler and Oil Tank
After digging our trench we started the process to install our FlowGuard waterproofing system. This process starts by us installing perforated pipe around the perimeter of the basement.
Behind The Oil Tank
After digging our trench we started the process to install our FlowGuard waterproofing system. This process starts by us installing perforated pipe around the perimeter of the basement.
Back Wall of The Basement
After digging our trench we started the process to install our FlowGuard waterproofing system. This process starts by us installing perforated pipe around the perimeter of the basement.
Right Side of The Basement
After digging our trench we started the process to install our FlowGuard waterproofing system. This process starts by us installing perforated pipe around the perimeter of the basement.
Working Smarter Not Harder
After we installed our perforated pipe we then cover it up with gravel. In order to get it down the stairs quickly and efficiently we built a slope system in order to bring everything down and send the empty buckets up quickly.
Front Wall of The Basement
Once all our gravel was down we started covering our system up in order for water to have a path of least resistance and lead to our sump pump, as well as to prepare to refinish the area with concrete.
Left Side of The Basement
Once all our gravel was down we started covering our system up in order for water to have a path of least resistance and lead to our sump pump, as well as to prepare to refinish the area with concrete. .
Our Basin
Once all our gravel was down we started covering our system up in order for water to have a path of least resistance and lead to our sump pump, as well as to prepare to refinish the area with concrete.
Back Wall of The Basement
Once all our gravel was down we started covering our system up in order for water to have a path of least resistance and lead to our sump pump, as well as to prepare to refinish the area with concrete.
Right Side of The Basement
Once all our gravel was down we started covering our system up in order for water to have a path of least resistance and lead to our sump pump, as well as to prepare to refinish the area with concrete.
Cutting Time
Before concreting over everything we installed Brightwall on their walls. This product gives their basement a finished look as well it brightens everything up as well.
First Wall Is Done
Before concreting over everything we installed Brightwall on their walls. This product gives their basement a finished look as well it brightens everything up as well.
Installing Brightwall
Before concreting over everything we installed Brightwall on their walls. This product gives their basement a finished look as well it brightens everything up as well.
Second Wall is Done
Before concreting over everything we installed Brightwall on their walls. This product gives their basement a finished look as well it brightens everything up as well.
Final Wall Is Done
Before concreting over everything we installed Brightwall on their walls. This product gives their basement a finished look as well it brightens everything up as well.
Fully Assembled TripleSafe
An inside look into our basin with our fully assembled TripleSafe sump pump before the airtight lid was installed and concreted over.
On Lockdown
Once our TripleSafe Sump pump was fully installed we installed our airtight lid, which insures that nothing can get in or out.
Fully Assembled TripleSafe
After installing and assembling our TripleSafe Sump pump we drilled the proper diameter holes in the block foundation in order to tie it into our discharge line.
Left Side of The Basement
Before concrete was applied we laid all of our FlowGuard around the perimeter of the basement.
Back Wall of The Basement
Before concrete was applied we laid all of our FlowGuard around the perimeter of the basement.
Right Side of The Basement
Before concrete was applied we laid all of our FlowGuard around the perimeter of the basement.
Left Side Of The Basement Completed
Here we can see how the left side of the basement turned out once we completed this project.
Left Side of The Basement With Our TripleSafe Completed
Here we can see how the left side of the basement turned out along with our TripleSafe sump once we completed this project.
Back Wall of The Basement Completed
Here we can see how the back wall by the boiler and oil tank turned out once we completed this project.
Right Side of The Basement Completed
Here we can see how the right side of the basement turned out once we completed this project.
And That's A Wrap On The Inside
Wide angle of how this project came out.
Discharge Line To Daylight
After installing our systems in the basement we installed the final piece to the puzzle.